Macomb’s new $44 million water plant should be operational by late August 2028, Public Works Director Alice Ohrtmann told the City Council on Monday.
The Illinois Environmental Protection Agency will review the project and examine the city’s construction permit application through Jan. 29, 2026, Ohrtmann said. The loan approval process should be completed around July 20, with construction beginning in August.